Earned value project tracking template

Earned value project tracking template
A project can be «on schedule» and still be costing more than planned, and the usual progress report does not show it: it says that fifty percent of the budget has been spent and that forty-five percent of the work is done, and leaves the reader to draw the conclusion. Earned value turns those two sentences into a comparison. This template does the arithmetic activity by activity: you type the budget for each one, the percentage that should be complete at the cut-off date and the percentage that actually is, and the sheet returns three money figures and two indices. What gets discussed in the meeting stops being an impression and becomes a subtraction.
The underlying idea is old and simple, and it is rarely used on small projects because it sounds like a large project office. If the budget is split across activities, each activity carries a value; progress is measured as the part of that value already delivered, not as effort spent or calendar consumed. A project that has used half its schedule and delivered a third of its value is behind, even if no deadline has been missed yet. The sheet translates that into three money columns and two indices, and leaves the judgement to whoever reads it.
The workbook is small on purpose: one sheet of nine columns and twenty rows, plus a four-point instruction sheet. No macros, no pivot tables, nothing to enable when you open it. Only four items are typed by hand per activity — budget, planned percentage, actual percentage and actual cost — and everything else is a formula already sitting in the cells, ready to be dragged down if the project needs more than twenty activities. That economy is deliberate: a workbook that takes ten minutes to fill in gets updated every two weeks; one that takes an hour gets updated once and abandoned.
What the sheet calculates and what the number is for
The three money columns are the same budget seen in three ways. Planned value, which the file calls PV, is what should be complete at the cut-off date valued at budget: the activity budget times the planned percentage. Earned value, EV, is what is complete, valued with the same budget: the budget times the actual percentage. Actual cost, AC, is what it cost to get there, and the sheet does not calculate it: it comes from the accounting system. All three are in the same unit — the budget currency — which is why they can be subtracted and divided against each other; comparing a progress percentage with a spend percentage compares two unrelated things.
From there come the two indices, which are the real output. SPI divides earned value by planned value and answers one question: of all the work the calendar promised for this date, how much was delivered. An SPI of 0.82 means that for every unit of work promised, eighty-two cents were delivered, an eighteen percent delay measured in money rather than days. CPI divides earned value by actual cost and answers a different question: for every unit spent, how much value was generated. A CPI of 0.94 says the project is buying value at a higher price than it budgeted, and that sentence can be said in a meeting without arguing about where it came from.
The pair matters more than either index alone. Low SPI with high CPI describes a slow but cheap project: sometimes that is a conscious choice — quality was preferred, or a supply was awaited — and sometimes it means the remaining work is precisely the expensive part. High SPI with low CPI is the rushed ending: progress is fast and spending is over, and the overrun shows up when there is no margin left. Both indices below one is the case the third instruction states plainly: it is not fixed by working faster with the same money.
With that pair in hand four decisions are typical: add resources to the activity dragging the project, renegotiate scope with the client before the overrun is irreversible, warn about the deviation while it can still be absorbed, or close an activity that adds no value and releases budget. The sheet makes none of those decisions. It removes the argument about the diagnosis so the argument can be about what to do.
The two sheets and the nine columns
The «Earned value» sheet has three header rows and twenty data rows. The first row carries the title in a dark band across all nine columns; the second, a subtitle announcing the content: PV, EV and AC per activity, with SPI, CPI and a cost forecast. The third, right-aligned, is the version line: «F49 · v1.0 · [DD/MM/YYYY]», where the bracket is a reminder to type the cut-off date. Below it the header row is a lighter grey with bold white text, carries an autofilter, and the sheet is frozen from row five, so the titles do not scroll away on a long project. Calculated cells are shaded pale grey: at a glance you can tell what is typed and what is read.
The formats say something too. The budget and the three money columns use a number format with two decimals and a thousands separator, with no currency symbol, so the workbook works in pesos, soles or euros without changes. Both percentages carry one decimal and a percent sign. Both indices carry two decimals, which is the right precision: an SPI of 0.8234 adds nothing that 0.82 does not say, and it invites the belief that the measurement is finer than it is.
The «Instructions» sheet is a narrow column with four numbered points. The first asks for the budget of each activity and both percentages at the cut-off date. The second defines the three figures in one line: PV is what should be done in money, EV is what is done valued at budget, AC is what it cost. The third explains how to read the indices and warns that both being low is not solved by speeding up. The fourth gives the only forecast formula in the workbook: the estimated final cost is the total budget divided by CPI.
| Column | What is typed or calculated | What it means |
|---|---|---|
| A · Activity | Typed. The deliverable or budget chapter name | The unit of progress; too fine and nobody updates it |
| B · Budget (BAC) | Typed. The approved budget for that activity | The total value the activity contributes to the project |
| C · % planned | Typed. How much should be complete at the cut-off date | Comes from the approved schedule, not from anyone's expectation |
| D · % actual | Typed. How much is really complete | Measured with evidence: deliverable accepted, milestone signed, work verified |
| E · PV | Formula: budget times planned percentage | The work promised for this date, in money |
| F · EV | Formula: budget times actual percentage | The work delivered, valued at the same budget |
| G · AC | Typed. Cost incurred for the activity to the cut-off date | What it cost per the books; not what is committed |
| H · SPI | Formula: EV divided by PV | How much of the promised value was delivered; below one is delay |
| I · CPI | Formula: EV divided by AC | How much value each unit of cost produces; below one is overrun |
It helps to read the table as a division of responsibilities. Of the nine columns, four are filled by hand and two of those four are not produced anywhere inside the sheet: the budget comes from project approval and the actual cost comes from the accounting system. The sheet contributes only the planned percentage, a schedule figure, and the actual percentage, the single judgement made by the person reporting. If those four inputs are sound, the indices are sound. If the actual percentage is written from memory, the workbook returns a two-decimal figure that looks exact and is not.
The four formulas and why the cell stays blank
The formulas are simple arithmetic wrapped in a conditional. Planned value is budget times planned percentage; earned value is budget times actual percentage; SPI divides EV by PV and CPI divides EV by AC. Each one is guarded by a conditional that returns an empty string when its input is missing: no budget means the three money columns stay blank; a planned value of zero leaves SPI blank; an actual cost of zero leaves CPI blank.
That guard is not a technical ornament, it is what makes the file usable. Without it the first empty row would display the division-by-zero error, and a workbook that looks broken on its first sheet stops being used. With it, rows without data look clean and the autofilter can hide them without dragging errors along. The trade-off is that a blank cell is ambiguous: it can mean the input is missing or that the result does not apply, which is why it is worth filling all twenty rows or deleting the ones not in use.
One case confuses people and the formula does not distinguish it: when the planned percentage is above zero and the actual is zero, SPI is calculated and returns zero. That is not a fault of the workbook; it is the statement that work was promised for this date and none was delivered. That zero is hard information and should be read as such. When both percentages are zero — an activity that has not started and was not planned for this cut-off either — SPI is also blank, because the division is meaningless. The difference between zero and blank is the difference between «none of what was due is done» and «it was not due yet».
The example the workbook ships with
The file arrives loaded with four activities from a small building job, enough to show the three cases that matter. «Diseño» (design) is one hundred percent planned and one hundred percent actual, with a cost of eleven million eight hundred thousand against a twelve million budget: the only healthy stretch in the example. «Obra gris» (structural work) should be at sixty percent and sits at fifty, with twenty-six million spent against forty-eight. «Instalaciones» (services) should be at thirty and is at twenty, with six million two hundred thousand spent against twenty-six. «Acabados» (finishes) was planned at just ten percent, has not started and carries no cost: the row that explains why CPI comes back blank.
| Activity | BAC | PV | EV | AC | SPI | CPI |
|---|---|---|---|---|---|---|
| Diseño (design) | 12,000,000 | 12,000,000 | 12,000,000 | 11,800,000 | 1.00 | 1.02 |
| Obra gris (structure) | 48,000,000 | 28,800,000 | 24,000,000 | 26,000,000 | 0.83 | 0.92 |
| Instalaciones (services) | 26,000,000 | 7,800,000 | 5,200,000 | 6,200,000 | 0.67 | 0.84 |
| Acabados (finishes) | 18,000,000 | 1,800,000 | 0 | 0 | 0.00 | — |
Adding the four rows, the total budget is one hundred and four million; planned value at the cut-off date is fifty million four hundred thousand; earned value is forty-one million two hundred thousand; actual cost is forty-four million. The project is therefore running at an SPI of 0.82 and a CPI of 0.94: late and expensive at the same time. Following the fourth instruction, the estimated final cost lands near one hundred and eleven million, about seven million above the approved budget. None of those figures is written in the file: they come from summing the columns and dividing, which is exactly what the workbook leaves visible so it can be checked.
The example also teaches not to read indices out of context. The «Acabados» row shows an SPI of zero, which a badly built dashboard would read as a disaster and which actually means the activity has not started. «Instalaciones» is the row that deserves the conversation: it combines delay and overrun worst, and it should be reviewed first even though its budget is half of the structural work. And «Diseño», with its CPI of 1.02, proves that a project can have one healthy activity and still be sick overall. The figures are illustrative and must be replaced: the sheet carries no currency symbol precisely so they can be typed in whichever one applies.
How to fill it in, step by step
The order matters more than it seems. First fix the cut-off date and type it in the version line; without that date the percentages mean nothing, because «fifty percent» only exists relative to a day. Then list the activities at a level you can measure: a work package, a deliverable, a phase. Too fine and nobody updates it; too coarse and the index hides the problem inside an average. Around twenty rows is usually the point where a mid-sized project can be reported in one working session.
The third step is to split the approved budget across those activities, leaving none at zero and inventing no contingency line that nobody later knows how to charge. The fourth is to copy the planned percentage from the approved schedule, not from the reporter's expectation: if the schedule said sixty percent was due at this date, type sixty even if the team believes less was really due. The fifth is the delicate one, the actual percentage, and it has only one defensible criterion: evidence. A deliverable accepted, a milestone signed, a quantity of work executed and verified. Effort is not progress, and hours worked do not turn an unfinished job into eighty percent.
The sixth step is actual cost, which is not estimated: it is taken from the accounting of that activity at the same cut-off date. Here a distinction changes the result and deserves to be written down: actual cost is cost incurred, not cost committed. A purchase order issued, a contract signed or an invoice received but not yet booked is not actual cost; charging it makes CPI look better than it is and the overrun arrives all at once two months later. If the accounting system cannot separate cost by activity, the workbook loses precision and that should be said when presenting it, instead of spreading the total by eye.
The seventh step is maintenance: if the project needs more than twenty activities, insert rows and copy the formula from the row above; never type a number over a grey cell. The eighth is discipline: save each cut-off as a separate file with the date in the name, and do not correct the past. A cut-off corrected backwards makes two periods impossible to compare, and that comparison is the only way to know whether the project is improving or worsening.
How to read the result: SPI, CPI and the forecast
The first reading mistake is averaging the row indices. The SPI in the example, averaged by hand, would give 0.63; the consolidated figure is 0.82, and the gap is not a detail: a simple average treats a twelve million activity the same as a forty-eight million one. The project index is calculated by summing first — total earned value over total planned value, total earned value over total cost — and dividing afterwards. That is why the workbook ships no totals row with indices already computed: it would force an argument about what gets added and what does not.
The final cost forecast follows the fourth instruction: total budget divided by CPI. With the example data, one hundred and four million divided by 0.9364 gives a little over one hundred and eleven million. Two figures follow that are used with the client or the board: the estimated cost to complete, which is that forecast minus what has been spent — about sixty-seven million — and the final deviation, the budget minus the forecast, here negative by roughly seven million. All three take two minutes by hand and are worth noting beside the cut-off rather than inside the sheet.
The forecast carries fine print that should be said out loud: it assumes the project will keep spending at today's efficiency. If the deviation comes from a one-off overrun already behind you, the forecast exaggerates; if it comes from structural inefficiency, it is right or optimistic. It is also unstable early on: with twenty percent of value delivered, a one-point change in the actual percentage moves CPI and the forecast far more than at eighty percent. That is why the number is recalculated at every cut-off and read as a warning rather than a sentence; its value is in appearing early, while something different can still be done.
Common mistakes and what the workbook does not solve
The most common mistake is an optimistic actual percentage. A team that has been at ninety percent of a task for weeks and never closes it produces an inflated EV, a CPI that looks fine and a delay that materialises at the end. The second is charging only invoiced amounts to actual cost: CPI improves artificially and the overrun appears when the invoices for work already done arrive. The third is mixing cut-off dates: a percentage at the twentieth with a cost at the thirtieth produces indices that describe no reality at all.
The fourth is averaging indices, already covered, and the fifth is structural: adding new activities without copying the formulas, or typing a value into a calculated column because «the number did not work out». When that happens the workbook stops being a calculation and becomes an opinion with formatting. The sixth is changing the approved budget mid-project with no record: BAC stops being the reference and every earlier index becomes incomparable.
Some limits are worth declaring before someone finds them in a meeting. The workbook has no time-phased baseline: planned value comes from a percentage typed at the cut-off date, not from a curve you can query for any day, so it draws no S-curve and shows no project history. It holds no start and end dates per activity, so it calculates no earned schedule and projects no completion date. It has no cells for final cost, cost to complete or deviation: those three are calculated outside, as described. It has no totals row, no permissions, no audit trail and no currency conversion.
And it replaces neither the accounting nor the contract. CPI inherits the quality of cost allocation: if cost is spread by rough criteria, the index is rough. Earned value does not say whether the work is any good either; a deliverable accepted grudgingly counts the same as a flawless one. The workbook measures execution against budget, and that is all it promises.
The sheet on screen
The cover shows the sheet with the example loaded. You can see the dark title band across the full width, the subtitle with the three figures and the two indices, and the version line on the right with the date placeholder. Below it the header row in grey with white text, and the four rows of the building job: design closed, structure halfway, services behind and finishes not started. Calculated columns are told apart by the pale shading, and the gap in CPI on the last row is exactly the case the workbook wants to show.

The image also shows that no cell carries a currency symbol and that amounts use a thousands separator: the file is meant to travel between countries and to let each business set its own currency when opening it, fixing the number format once. It is worth saving one copy per cut-off with the date in the file name, writing that same date in the version line and leaving earlier cut-offs untouched. With that, two or three consecutive files show whether SPI is rising or falling, which is the information a single cut-off cannot give.
The sheet does one thing and does it in five columns: it turns project progress into comparable money and returns two indices that can be discussed with numbers. With that, resources can be reassigned, a deviation flagged in time and the activity dragging the rest identified, without waiting for the closing report. Kardex Tauro publishes this template alongside the rest of its Excel library, so tracking happens at the cut-off and not at the post-mortem.